Second Niger Bridge to be completed on May 15 – Fashola

0
141
The Minister of Works and Housing, Mr. Babatunde Fashola.

Minister of Works and Housing, Babatunde Fashola, has given May 15 as the expected date of delivery of the Second Niger Bridge with four kilometres to completion.

Fashola made the disclosure during a live appearance on Channels Television’s “The 2023 Verdict” on Monday.

Asked when the project would be delivered, he said, “What we expect is around the 15th of May, thereabout, is the timeline we have…. The bridge is finished; one side of the link road is completed. It remains four kilometres of work.”

On the ever-changing expected dates of delivery, the minister reiterated the role of “local circumstances”, such as the sit-at-home order every Monday for the last two years, which according to him had slowed down the work.

Advertisement

“If you look at the number of days we’ve lost over two years, you must factor it into some of these moving targets,” he said.

Fashola also stated that there were compensation issues people were not aware of, including the relocation of 132kVA transmission lines and a power shutdown.

The minister said that the administration of President Muhammadu Buhari deserved praise because, according to him, his principal’s 2015 campaign promised to boost the economy, infrastructure was not central to the three-point agenda. (Channels TV)